Type: Core Program
Phase: Construction
Reimbursement Rate: 65.74%
Total Budget: $229,965,633
Est. Max Total Facilities Grant *: $96,854,000
Est. Completion: June, 2028
Type: Green Repair
Phase: Final Audit Approved
Reimbursement Rate: 57.74%
Total Budget: $2,271,329
Est. Max Total Facilities Grant *: $0
Est. Completion:
Type: Accelerated Repair
Phase: Closeout
Reimbursement Rate: 58.37%
Total Budget: $780,515
Est. Max Total Facilities Grant *: $381,937
Est. Completion:
Type: Accelerated Repair
Phase: OPM Selection
Reimbursement Rate:
Total Budget:
Est. Max Total Facilities Grant *: $0
Est. Completion:
Type: Accelerated Repair
Phase: OPM Selection
Reimbursement Rate:
Total Budget:
Est. Max Total Facilities Grant *: $0
Est. Completion:
Type: Accelerated Repair
Phase: OPM Selection
Reimbursement Rate:
Total Budget:
Est. Max Total Facilities Grant *: $0
Est. Completion:
Type: Accelerated Repair
Phase: Final Audit Approved
Reimbursement Rate: 56.89%
Total Budget: $968,569
Est. Max Total Facilities Grant *: $446,329
Est. Completion: August, 2017
Type: Accelerated Repair
Phase: OPM Selection
Reimbursement Rate:
Total Budget:
Est. Max Total Facilities Grant *: $0
Est. Completion: